Construction of 110/15 kV Kluczewo substation

In December 2007 on behalf of ENEA SA (Szczecin Department) we have started construction of 110/15 kV Kluczewo substation in the Pomeranian Special Economic Zone (PSSE) near Stargard Szczeciński. The substation will supply electricity for companies located in the PSSE, mainly for Bridgestone tyre plan.

The scope of work includes:
- construction of 110 kV switchyard with following layout: two feeder bays, two cable bays, coupling bay;
- foundation for technological container wiyh MV switchgear as well as installation of protection and control systems.
Expected completion date of works - end of March 2008.

 
 